Bridge design error leads to a year’s delay and millions more in cost

A design error about the installation of a bridge over the River Witham and the East Coast main line will delay completion of the Grantham relief road and add millions to the cost.

County Councillor Richard Davies said: “The complexities of designing and constructing this relief road, particularly this bridge, are far beyond what we as a council can do directly.

“That’s why top international engineering companies and experienced contractors were entrusted to handle the project. Although we oversee the scheme as a whole, we rely on our suppliers’ combined expertise.

“When undertaking a project of the magnitude, all design work also undergoes a mandatory, additional layer of independent checking. Unfortunately, despite all of this, a mistake was made along the way that’s led to this new delay.

“This mistake related to the how the bridge was to be installed, and us being told it couldn’t be pushed into place as intended due to concerns relating to specific wind conditions.

“Safety comes first, so the work was halted so our designers and contractors could address the problem.

“We’ve done everything you could reasonably expect us to do as the client for the scheme, but we feel we’ve been let down. The important thing is that the details of the solution are nearly finalised, meaning we can start pushing the bridge into place in the coming months.”

The relief road is now expected to open in 2026, a year later than expected, with rectification expected to cost up to £20m, bringing the project’s expected total to £158-168 million.

Cllr Davies said: “Let me be 100% clear: while we may need to cover these extra costs initially, we will ensure that those responsible for this are held accountable and that every penny of taxpayer money will be recovered.

“We are pursuing contractual and legal processes as a result of this error so are unable to comment any further on this at this stage for legal reasons.

“For now, our priority now is getting this massive project back on track as soon as possible – and that means continuing to work closely with our appointed contractor and designers.”

Once it begins, the bridge push over the 293-metre span will take several months as it crosses the rail line during periods when trains have stopped running.

The rest of the structure will then be built on the east side of site, including lifting new steel beams into place.

Several more months will then be spent concreting the decks, installing safety barriers, and laying road surfacing.

Cllr Davies ended: “While this new delay is incredibly disappointing, we remain 100% committed to completing Grantham’s relief road.

“As a local resident and business owner, I understand and share the frustration this delay will cause. But safety comes first, and even the smallest risk must be taken extremely seriously.

“In the meantime, I want to thank everyone for their continued patience as we work towards completing this monumental project.”

 

A message from the Editor:

Thank you for reading this story on our news site - please take a moment to read this important message:

As you know, our aim is to bring you, the reader, an editorially led news site and magazine but journalism costs money and we rely on advertising, print and digital revenues to help to support them.

With the Covid-19 pandemic having a major impact on our industry as a whole, the advertising revenues we normally receive, which helps us cover the cost of our journalists and this website, have been drastically affected.

As such we need your help. If you can support our news sites/magazines with either a small donation of even £1, or a subscription to our magazine, which costs just £27.55 per year, (inc p&P and mailed direct to your door) your generosity will help us weather the storm and continue in our quest to deliver quality journalism.

As a subscriber, you will have unlimited access to our web site and magazine. You'll also be offered VIP invitations to our events, preferential rates to all our awards and get access to exclusive newsletters and content.

Just click here to subscribe and in the meantime may I wish you the very best.

Advertisment












Latest posts

Report reveals £2.1bn economic boost from redevelopment of former RAF Scampton

An independent report has revealed a £2.1bn economic boost from the redevelopment of the former RAF Scampton. The report produced by Focus Consultants was commissioned...

Works to begin on Crown House area as Rosegarth Square redevelopment progresses

The transformation of Crown House within the wider Rosegarth Square redevelopment site in Boston is now moving forward, with foundation works set to begin next week. Plans were...

Time capsule uncovered during Freshney Place works

A time capsule has been discovered during redevelopment works at Freshney Place in Grimsby, hidden behind the foundation stone of the former Riverhead Centre. The...

Lincoln Minster School makes waves with British Rowing

Lincoln Minster School’s rowing programme has rapidly transformed from a casual co-curricular option into a thriving, competitive sport—propelled by student ambition, community support, and an...

Locals’ art goes on display at Usher Gallery

Visitors now have the chance to view more than 120 works of art from Lincolnshire’s artists in a new exhibition at Lincoln’s free public...

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close