Friday, December 5, 2025

Bridge design error leads to a year’s delay and millions more in cost

A design error about the installation of a bridge over the River Witham and the East Coast main line will delay completion of the Grantham relief road and add millions to the cost.

County Councillor Richard Davies said: “The complexities of designing and constructing this relief road, particularly this bridge, are far beyond what we as a council can do directly.

“That’s why top international engineering companies and experienced contractors were entrusted to handle the project. Although we oversee the scheme as a whole, we rely on our suppliers’ combined expertise.

“When undertaking a project of the magnitude, all design work also undergoes a mandatory, additional layer of independent checking. Unfortunately, despite all of this, a mistake was made along the way that’s led to this new delay.

“This mistake related to the how the bridge was to be installed, and us being told it couldn’t be pushed into place as intended due to concerns relating to specific wind conditions.

“Safety comes first, so the work was halted so our designers and contractors could address the problem.

“We’ve done everything you could reasonably expect us to do as the client for the scheme, but we feel we’ve been let down. The important thing is that the details of the solution are nearly finalised, meaning we can start pushing the bridge into place in the coming months.”

The relief road is now expected to open in 2026, a year later than expected, with rectification expected to cost up to £20m, bringing the project’s expected total to £158-168 million.

Cllr Davies said: “Let me be 100% clear: while we may need to cover these extra costs initially, we will ensure that those responsible for this are held accountable and that every penny of taxpayer money will be recovered.

“We are pursuing contractual and legal processes as a result of this error so are unable to comment any further on this at this stage for legal reasons.

“For now, our priority now is getting this massive project back on track as soon as possible – and that means continuing to work closely with our appointed contractor and designers.”

Once it begins, the bridge push over the 293-metre span will take several months as it crosses the rail line during periods when trains have stopped running.

The rest of the structure will then be built on the east side of site, including lifting new steel beams into place.

Several more months will then be spent concreting the decks, installing safety barriers, and laying road surfacing.

Cllr Davies ended: “While this new delay is incredibly disappointing, we remain 100% committed to completing Grantham’s relief road.

“As a local resident and business owner, I understand and share the frustration this delay will cause. But safety comes first, and even the smallest risk must be taken extremely seriously.

“In the meantime, I want to thank everyone for their continued patience as we work towards completing this monumental project.”

 

Advertisment












Latest posts

New council–industry collaboration supports manufacturers through upcoming reforms

North Lincolnshire Council has brought together senior leaders from the region’s major manufacturers to outline the operational impact of employment law changes scheduled for...

Planning approval granted for new 89-home scheme in Fishtoft

A major residential scheme has secured detailed planning permission for 89 new homes on land off Gaysfield Road in Fishtoft, Lincolnshire. The project covers...

Work underway to prepare Grimsby’s new Alexandra Dock housing site for construction

Work is undeway to prepare Grimsby Town Centre’s new Alexandra Dock housing site for full construction to start early in 2026. Ahead of the main...

Lincolnshire’s young people turning to AI for support, company and advice

North East Lincolnshire youth charity Horizon Youth Zone, part of the OnSide Network, is raising concerns about growing digital dependence and a lack of...

Lincoln ramps up festive fun with city-wide Christmas craft workshops

Lincoln’s parks are gearing up for a busy December as a full programme of Christmas craft workshops opens to adults, teens, and children. The...

By continuing to use the site, you agree to the use of cookies. more information

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close