Works are well underway on the first phase of a business park which will unlock new jobs for North Kesteven.
Phase one of the 37-acre Sleaford Moor Enterprise Park is expected to complete by August next year, ready for the first businesses to move in and call it home.
Local contractor Smith Construction is carrying out the initial enabling groundworks for plots one and three to be built, which make up this phase along with the civils and spine road. Harlaxton Engineering based in Grantham meanwhile are delivering the site-wide utilities connections for the park.
Within plot one will be nine business units ranging from 1,313 sq ft to 2,066 sq ft benefitting from solar panels, energy efficient insulation and electric vehicle charging points.
Plot three contains six slightly larger grow-on business units ranging from 3,369 sq ft to 5,123 sq ft benefitting from solar panels, an electric vehicle charging shelter and extra efficient insulation.
North Kesteven District Council leader councillor Richard Wright said: “To stand onsite where in just under a year’s time there’s expected to be finished units ready to welcome businesses is just fantastic. It’s a real moment to celebrate as a Council committed to investing in our communities, and something to be proud of together as a District.
“There’s been great levels of interest in Sleaford Moor Enterprise Park so far and our marketing agent Banks Long & Co continues to actively promote it and liaise with potential tenants.
“I look forward to seeing the site develop as we reach the next stages of construction, and of course the ripple effect I hope Sleaford Moor Enterprise Park will have in encouraging carbon and energy-saving features to be embedded into other business parks and commercial developments elsewhere.”